Hot Springs
Two areas in the Hot Springs exchange (rural), including the Angostura East and Minnekahta West areas will be upgraded to Fiber in 2024.
Contractors:
Wiring Contractor – Vantage Point
Engineering Consultant – Heberly & Associates
Construction Contractor – MasTec North America
Update Contact Information & Win
2024 PROJECT UPDATE
December 19, 2024
Hot Springs Angostura
- MasTec has completed main line construction.
- Crews are nearly finished with plowing lines to customer premises.
- Crews will be off through the end of the year for the Christmas and New Year’s holidays.
Hot Springs Minnekahta
- MasTec splicers are working along US Highway 18 and Memorial Road.
- Crews will be off through the end of the year for the Christmas and New Year’s holidays.
December 12, 2024
Hot Springs Angostura
- MasTec has a plow crew working at the southern end of the project along Rapid Avenue, Deadwood Avenue, Beach Street, and Lakeview Street.
- One drop crew is placing fiber to customer homes along Brook Drive, Hillside Road, and Twin Rock Bend Road.
- A second drop crew is working along Recreation Road.
- The third drop crew is on Killdeer, Waterview, and Ridge Roads.
Hot Springs Minnekahta
- MasTec has a bore crew working on private driveways off Albatross Lane, Woodland Drive, and Red Fox Road.
- A crew plowing lines to customer homes is working along private drives off US Highway 18, Woodland Drive, and Red Fox Road.
December 5, 2024
Hot Springs Angostura
- MasTec has a plow crew working on Brook Drive.
- One drop crew is placing fiber to customer homes along N Angostura Road, Hillsview Drive, and Twin Rock Bend Road.
- A second drop crew is working along N Angostura Road and Horse Camp Road.
- The third drop crew is on Shoreview, Waterview, and Ridge Roads.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a plow crew working on private driveways off Memorial Road, Country Club Drive, and Red Fox Road.
- A crew plowing lines to customer homes is working along private drives off Country Club Drive, US Highway 18, and Red Fox Road.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
November 21, 2024
Hot Springs Angostura
- MasTec has a plow crew working along Ty Road, then moving to Brook Drive.
- One drop crew is placing fiber to customer homes along Todd, Greg, Renee, Denise, and Nyla Drives.
- A second drop crew is working along Shoreview Drive, Evergreen Lane, Ridge Road, and Waterview Road.
- The third drop crew is on Circle Court, Pebble Court, Ridge Road, Boaters Boulevard, and Cove Road.
- Two bore crews are working in the neighborhood at the southeast corner of Angostura Reservoir.
- Crews are working next week on Monday and Tuesday. They will be off for Thanksgiving and will return on December 2.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a plow crew working on private driveways off Memorial Road.
- A crew plowing lines to customer homes is working behind the plow crew off Memorial Road. The bore crew is also working in this area.
- Crews are leaving Saturday for a break over the week of Thanksgiving. They will return to work on December 3.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
November 14, 2024
Hot Springs Angostura
- MasTec has a plow crew working along Brook Drive and Ty Road.
- One drop crew is placing fiber to customer homes along Todd, Greg, Renee, Denise, and Nyla Drives.
- A second drop crew is working along Hillsview Drive, then will move to Todd Drive.
- The third drop crew is on Circle Court, Pebble Court, Ridge Road, Boaters Boulevard, and Cove Road.
- Two bore crews are working in the neighborhood at the southeast corner of Angostura Reservoir.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a plow crew working on a private driveway south of Stag Glen Road.
- A second crew is plowing along Stag Glen Road.
- The bore crew is working along Stag Glen Rodd and the private drive ahead of the plow crews.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
November 7, 2024
Hot Springs Angostura
- MasTec has a plow crew working along Summersun Lane, N Dam Road and Knappie Road.
- One drop crew is continuing to bury fiber to customer homes along Fall River Road including Garden Drive, Wild Turkey Lane, and Eagle Rock Road.
- The other drop crew is working along Angostura at Lakeview Court, Pebble Court, Ridge Road, Boater’s Boulevard, and US Hwy 385.
- One bore crew is still working along Summersun Drive, N Dam Road, and Knappie Road.
- The other bore crew is continuing along N Angostura and Recreation Roads.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a plow crew working along Memorial Road north of Stag Glen Road.
- A second crew is plowing along Mower Road.
- The bore crew is working along Memorial and Mower Roads in front of the plow crew.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
October 31, 2024
Hot Springs Angostura
- MasTec has a plow crew working along Summersun Lane, N Dam Road and Knappie Road.
- One drop crew is continuing to bury fiber to customer homes along Fall River Road including Garden Drive, Wild Turkey Lane, and Eagle Rock Road.
- The other drop crew is working along Angostura at Lakeview Court, Pebble Court, Ridge Road, Boater’s Boulevard, and US Hwy 385.
- One bore crew is still working along Summersun Drive, N Dam Road, and Knappie Road.
- The other bore crew is continuing along N Angostura and Recreation Roads.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a plow crew working along Memorial Road north of Stag Glen Road.
- A second crew is plowing along Mower Road.
- The bore crew is working along Memorial and Mower Roads in front of the plow crew.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
October 24, 2024
Hot Springs Angostura
- MasTec has a plow crew working along Recreation Road between N Angostura Road and Breakers Beach marina.
- One drop crew is burying fiber to customer homes along Fall River Road including Garden Drive, Wild Turkey Lane, and Eagle Rock Road.
- The other drop crew is working along Boaters Boulevard, Pebble Court, Angostura Road, Smithwick Road, and Pirates Road.
- One bore crew is working along Summersun Drive, N Dam Road, and Knappie Road.
- The other bore crew is along N Angostura and Recreation Roads.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a plow crew working along Memorial Road north of Mower Road.
- A second crew is plowing along Mower Road and private drives off Memorial Road. This crew will then move to Erskine Road.
- The bore crew is working along Memorial and Mower Roads in front of the plow crew.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
October 17, 2024
Hot Springs Angostura
- MasTec has a plow crew working along Porky Court, Denise Drive, and Hillsview Drive. They will move to Brook Drive next week.
- One drop crew is burying fiber to customer homes along Fall River Road including Garden Drive, Wild Turkey Lane, Eagle Rock Road, and Scenic Road.
- The other drop crew is working along Boaters Boulevard, Cove Road, Barefoot Ridge Court, Angostura Rd, and Pirates Road.
- One bore crew is working along N Dam and Knappie Roads.
- The other bore crew is along N Angostura and Recreation Roads.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a plow crew working along Memorial Road, moving north.
- The crew plowing lines to customer homes is working on private drives off Memorial Road.
- The bore crew is working along Erskine Road in front of the plow crew.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
October 10, 2024
Hot Springs Angostura
- MasTec has a plow crew working along Brook Drive, Buena Vista Road, and Garden Drive.
- A crew will work on finishing the Eagle Valley Subdivision including Greg, Nyla, and Denise Drives.
- One drop crew is working along Fall River Road including Garden Drive, Wild Turkey Lane, Eagle Rock Road, and private drives to addresses along Fall River Road.
- The other drop crew is working along Boaters Boulevard, Rangeview Court, Cove Road, and Pirates Road.
- One bore crew is working along Recreation and N Dam Roads.
- The other bore crew is working in a housing development along Summersun Drive.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a plow crew working along Erskine Road, moving north.
- The crew plowing lines to customer homes is working along Red Fox Road, Woodland Drive and Country Club Drive.
- The bore crew is working along Erskine Road in front of the plow crew.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
October 3, 2024
Hot Springs Angostura
- MasTec’s main line plow crew is working along Horse Camp Road and Feeder Way, working back toward the highway.
- When additional equipment arrives, a crew will be finishing work in the Eagle Valley subdivision, including Greg, Nyla, and Denise Drives.
- A crew burying lines to customer premises is working along Fall River Road including Hillside Road, Garden Drive, and private driveways off Fall River Road.
- The other drop crew is working along Angostura Road, Boater’s Boulevard, Rangeview Court, Clover Ridge Court, and Ridge Road.
- One bore crew is working on Recreation Road and in the Marina area.
- The second bore rig is working along Recreation Road, completing road crossings.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has one plow crew working along Memorial Road about 2 miles north of Highway 18, from Erskine Road and north.
- The other plow crew is working along Red Fox Road and private drives off Highway 18 between Woodland Drive and Mule Deer Road. Lines to customer homes are being completed in these areas as well.
- The bore crew is working along Memorial Road and Erskine Road around the plow crews.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
September 26, 2024
Hot Springs Angostura
- MasTec’s main line plow crew is working along N Angostura Road between US Hwy 385/18 and Hills View Dr. They will move next to Horse Camp Road and Feeder Way, working back towards US Hwy 385/18.
- A crew will be finishing work in the Eagle Valley subdivision, including Greg, Nyla, and Denise Drives.
- The crew burying lines to customer premises is working along Fall River Road including Scenic and Hillside Roads.
- One bore crew is working on Recreation Road and in the Cascade Campground.
- The second bore rig is working along Recreation Road, completing road crossings.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a mainline plow and a drop crew working along Nickel Drive, Albatross Lane, and Country Club Drive.
- A second plow crew is working along Red Fox Road and private drives off Hwy 18 between Woodland Drive and Mule Deer Road.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
September 19, 2024
Hot Springs Angostura
- MasTec’s main line plow crew is working along N Angostura Road between Lake Resort Lane and Recreation Road.
- The crew burying lines to customer premises is working along Fall River Road including Scenic, Hillside, and Buffalo Grass Roads.
- One bore crew is working on Recreation Road.
- The second bore rig is working along Boaters Boulevard.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a mainline plow and a drop crew working along Mule Deer Road, Pass Road, and private drives along US Hwy 18.
- A second plow crew is working along Memorial Road, and private drives off Memorial.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
September 12, 2024
Hot Springs Angostura
- MasTec’s main line plow crew is working along N Angostura Road at Waterview Road, Killdeer Road, Offshore Road, Pelican Road, Shoreview Drive, Lake Resort Lane, and Recreation Road.
- The crew burying lines to customer premises is working along Fall River Road including Scenic, Hillside, and Buffalo Grass Roads.
- One bore crew is working near Angostura Road, then will move to N Angostura Road between Hills View Drive and Recreation Road.
- The second bore rig is working near Angostura Road to assist the plow crew as needed.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a mainline plow and a drop crew working along Nickel Drive, Country Club Drive, and private drives along US Highway 18.
- A second plow crew is working along Memorial Road, and private drives off Memorial.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
September 5, 2024
Hot Springs Angostura
- Crews are off this week. They will return to the project on September 9.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- Crews are off this week. They will return to the project on September 9.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
August 29, 2024
Hot Springs Angostura
- Crews will be off next week. They will return to the project on September 9.
- After the break, MasTec’s plow crew will work along N Angostura Road for a short stretch between US Hwy 385/18 and Hills View Drive. They will move next to finish the Eagle Valley Subdivision including roads Greg Drive, Nyla Drive, and Denise Drive.
- One bore crew will be working near Angostura Road along North and South Heartland Roads.
- The second bore crew will be along N Angostura Road between Waterview Road, Killdeer Road, Offshore Road, Pelican Road, Shoreview Drive, Lake Resort Lane, and Recreation Road.
- Vantage Point will have a technician in the area installing clamshells for customers who have recently ordered service.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- Crews will be off next week. They will return to the project on September 9.
- MasTec’s main line plow crew is working along Estates Road and Darline Lane.
- The drop crew will continue to place lines to customer homes along Estates Road, Dana Road, Darlene Lane, Clayton Drive, Whitetail Road, and Simunek Court.
- After the break, the crews will focus on Nickel Drive, Country Club Drive and private drives along US Hwy 18.
- Vantage Point will have a technician in the area installing clamshells for customers who have recently ordered service.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
August 22, 2024
Hot Springs Angostura
- MasTec’s plow crew is working along Boaters Boulevard. The crew will move to Bunny Drive and the private driveways along Bunny Drive.
- The plow will move next to N Angostura Road for a short stretch between US Hwy 385/18 and Hills View Drive.
- One bore crew is working again this week along N Angostura Road, Feeder Way Road, and Pebble Court.
- The second bore crew is along N Angostura Road between Waterview Road, Killdeer Road, Offshore Road, Pelican Road, Shoreview Drive, Lake Resort Lane, and Recreation Road.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec’s main line plow crew is working along Hwy 18 between Clubhouse Drive and Nickel Drive.
- The drop crew is continuing to place lines to customer homes along Estates Road, Dana Road, Darlene Lane, Clayton Drive, Whitetail Road, and Simunek Court.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
August 15, 2024
Hot Springs Angostura
- MasTec’s plow crew is working along Angostura Road between Highway 385 and Smithwick Road. The crew will then move to Boaters Boulevard. Afterward, they will head north along Angostura Road and complete side routes down Lake Vista Drive, Bunny Drive, and private drives along the way.
- The bore crew is working along N Angostura Road, Hills View Drive, and Feeder Way Road.
-
If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a bore crew, the rock bore operation, working along Highway 18 between Clubhouse Drive and Whitetail Road.
- The second bore crew is working along Whitetail Road between Highway18 and Coyote Road.
- The main line plow crew is also working side routes along private drives on Highway 18 near Memorial Road.
- The drop crew is placing lines to customer homes along Estates Road, Dana Road, Darlene Lane, Clayton Drive, Whitetail Road, and Simunek Court.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
August 1, 2024
Hot Springs Angostura
- MasTec’s plow crew is working along Oral Road between Hwy 385 and Angostura Road. They will move to N Angostura Road to place cable into the new Golden West building.
- The bore crew is still working along Porky Court, Denise Drive, and Tatanka Court (off Denise Drive).
- The drop crew is continuing to bury lines to customer homes on Ponderosa Road, Timber Road, US Hwy 18/385, Hill Side Road, Buffalo Grass Road, and Cheyenne Drive.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- Most of the construction crews are in the same areas as last week due to the rocky conditions.
- MasTec has a bore crew, the rock bore operation, working along Hwy 18 between Clubhouse Drive and Whitetail Road.
- The second bore crew is working along Hwy 18 near Memorial Road.
- The main line plow crew is also working along Hwy 18 near Memorial Road They will move to Turkey Track Road and Whitetail Road.
- The drop crew is placing lines to customer homes along Estates Road, Dana Road, Darlene Lane, Clayton Drive, and Taylor Lane.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
July 25, 2024
Hot Springs Angostura
- MasTec’s plow crew is working along Greg Drive between Renee Drive and Nyla Drive. They are also plowing along Nyla Drive between Greg Drive and Porky Court. The crew will then move to Denise Drive and Eagle Court.
- The bore crew is working along Porky Court, Denise Drive, and Tatanka Court (off Denise Drive).
- The drop crew is burying lines to customer homes on Ponderosa Road, Timber Road, US Hwy 18/385, Hill Side Road, Buffalo Grass Road, and Cheyenne Drive.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a bore crew, the rock bore operation, working along Hwy 18 between Clubhouse Drive and Whitetail Road.
- The second bore crew is working along Hwy 18 near Memorial Road.
- The main line plow crew is also working along Hwy 18 near Memorial Road.
- The drop crew is placing lines to customers homes along Estates Road, Dana Road, Darlene Lane, Clayton Drive, and Taylor Lane.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
July 18, 2024
Hot Springs Angostura
- MasTec has a main line plow on Todd Drive between Fall River Road and Greg Drive. They will move to Greg Drive between Todd Drive and Renee Drive.
- One bore crew is working along Shoreview Drive between Waterview Road and Sunny Slope Road. This crew is also working along Off Shore Road, Bunny Drive, and Sea Gull Road.
- A second bore crew is working along Ridge Road and Angostura Road, between US Hwy 18/385 and Feeder Way.
- The crew plowing lines to customer premises is on Ponderosa Road, Timber Road, US Hwy 18/385, Hill Side Road, Buffalo Grass Road, and Cheyenne Drive.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec’s rock bore crew is working along Hwy 18 between Clubhouse Drive and Whitetail Road.
- The second bore crew is working along Hwy 18 near Memorial Road.
- The drop crew is working along Estates Road, Dana Road, Darlene Lane, Clayton Drive and Taylor Lane.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
July 11, 2024
Hot Springs Angostura
- MasTec’s crews returned on Tuesday after the Independence Day break.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec’s crews returned on Tuesday after the Independence Day break.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
June 27, 2024
Hot Springs Angostura
- MasTec’s plow crew is working along US Hwy 385/18 (Fall River Rd) between Maverick Junction and Wild Turkey Lane.
- One bore crew is working along Fall River Road between Todd Drive and Greg Drive.
- Another bore crew is working along Angostura Road, between Lake Vista Drive and Recreation Road, moving south.
- The crews will be leaving for the Fourth of July holiday break on the 29th of June. They will return to the area on the 7th of July.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- One bore crew, the rock bore operation, is working along Hot Brook Canyon Road between Sandstone Road and Simunek Court.
- The second bore crew is working along Simunek Court.
- The plow crew is also working along Hot Brook Canyon Road between Sandstone Road and Simunek Court.
- Rock sawing has been completed in this area.
- The crews will be leaving for the Fourth of July holiday break on the 29th of June. They will return to the area on the 7th of July.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
June 20, 2024
Hot Springs Angostura
- MasTec’s plow crew is working along US Hwy 385/18 (Fall River Rd) between Maverick Junction and Brook Drive.
- One bore crew is working along Fall River Road, between Todd Drive and Greg Drive.
- Another bore crew is working along US Hwy 385, between N Angostura Road and Feeder Way, moving south.
- The crew plowing to customer homes is working along Ponderosa Road, Timber Road, and Spruce Drive.
- Vantage Point is scheduling the remaining clamshell installations.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec’s bore crew, the rock bore operation, is working along Estates Road between Hot Brook Canyon Road and Dana Road.
- The second bore crew is working along Darlene Lane and Dana Road.
- The plow crew is also working along Clayton Drive and Dana Road.
- The third bore crew is working along Hwy 18, west of town.
- Vantage Point is scheduling the remaining clamshell installations.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
June 13, 2024
Hot Springs Angostura
- MasTec’s plow crew is working along US Hwy 385/18 (Fall River Rd) between Maverick Junction and Brook Drive.
- One bore crew is working along Fall River Road, between Scenic Road and Todd Drive.
- Another bore crew is working along US Hwy 385, between N Angostura Road and Feeder Way, moving south.
- The crew plowing to customer homes is working along Ponderosa Road, Timber Road, and Spruce Drive.
- Vantage Point is scheduling the remaining clamshell installations.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec’s bore crew, the rock bore operation, is working along Hot Brook Canyon Road between Cold Brook Avenue and Estates Road.
- The second bore crew is working along Estates Road.
- The plow crew is also working along Estates Road.
- The third bore crew is working along Hwy 18, west of town.
- Vantage Point is scheduling the remaining clamshell installations.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
June 6, 2024
Hot Springs Angostura
- MasTec’s plow crew is working along US Hwy 385 between Maverick Junction/US Hwy 18 (Fall River Road) and Spring Canyon Road.
- One bore crew is working along Fall River Road, between US Hwy 385 and Scenic Road.
- Another bore crew is working along Old Hwy 79, between Hwy 385 and Angostura Road
- Vantage Point is scheduling the remaining clamshell installations.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- One bore crew, the rock bore operation, is working along Hot Brook Canyon Road between Cold Brook Avenue and Estates Road.
- The second bore crew is working on side routes along Hot Brook Canyon Road.
- The rock saw is working along Estates Road.
- The plow crew is working on side routes along Hot Brook Canyon Road which include private drives.
- Vantage Point is scheduling the remaining clamshell installations.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
May 30, 2024
Hot Springs Angostura
- MasTec’s crews were off on rotation over the Memorial Day weekend.
- Vantage Point is scheduling the remaining clamshell installations.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec’s crews were off on rotation over the Memorial Day weekend.
- Vantage Point is scheduling the remaining clamshell installations.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
May 23, 2024
Hot Springs Angostura
- MasTec’s plow crew is working along US Hwy 385 between Maverick Junction and Spring Canyon Road.
- The bore crew is along Fall River Road between US Hwy 385 and Scenic Road.
- Vantage Point is scheduling the remaining clamshell installations.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- Again this week, MasTec has a crew boring and another crew plowing cable along Hot Brook Canyon Road between Cold Brook Avenue and Estates Road.
- Crews are also working on side routes in this area, including private drives.
- Vantage Point is scheduling the remaining clamshell installations.
- If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
May 15, 2024
Hot Springs Angostura
- MasTec’s plow crew is working along US Hwy 385 between Maverick Junction and Cheyenne Drive. A second crew is boring along Fall River Road between Scenic and Buena Vista Roads.
- Vantage Point is nearly finished installing clamshells on customer premises. If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a crew boring and another crew plowing cable along Hot Brook Canyon Road between Cold Brook Avenue and Estates Road.
- Crews are also working on side routes in this area, including private drives.
- Vantage Point is nearly finished installing clamshells on customer premises. If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
May 3, 2024
Hot Springs Angostura
- MasTec has one crew boring and inserting pipe and one crew plowing along US Highway 385 between Maverick Junction and Spring Canyon Road.
- Vantage Point is nearly finished installing clamshells on customer premises. If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a boring crew and a crew constructing fiber to customer premises working along Hot Brook Canyon Road between Cold Brook Avenue and Estates Road.
- Crews are working on side routes along this area which include private drives.
- Vantage Point is nearly finished installing clamshells on customer premises. If you are in the project area and have not yet had a clamshell installed, please call Golden West at 1-855-888-7777 and ask for the engineering department.
April 25, 2024
Hot Springs Angostura
- MasTec has one crew boring and inserting pipe and one crew plowing along US Highway 385 between Maverick Junction and Spring Canyon Road.
- Vantage Point technicians are installing clamshells on customer premises.
- If you have any questions about scheduling or the installation process, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a boring crew and a crew constructing fiber to customer premises working along Hot Brook Canyon Road between Cold Brook Avenue and Estates Road.
- Crews are working on side routes along this area which include private drives.
- Vantage Point technicians are installing clamshells on customer homes.
- If you have any questions about scheduling or the installation process, please call Golden West at 1-855-888-7777 and ask for the engineering department.
April 19, 2024
Hot Springs Angostura
- MasTec has one crew boring and inserting pipe and one crew plowing along US Highway 385 between Maverick Junction and Spring Canyon Road.
- Vantage Point technicians are installing clamshells on customer premises.
- If you have any questions about scheduling or the installation process, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has a boring crew and a crew constructing fiber to customer premises working along Hot Brook Canyon Road between Cold Brook Avenue and Estates Road.
- Vantage Point technicians are installing clamshells on customer homes.
- If you have any questions about scheduling or the installation process, please call Golden West at 1-855-888-7777 and ask for the engineering department.
April 11, 2024
Hot Springs Angostura
- MasTec has one crew boring and inserting pipe and one crew plowing along US Highway 385 between Maverick Junction and Cheyenne River Road.
- Vantage Point technicians are installing clamshells on customer premises.
- If you have any questions about scheduling or the installation process, please call Golden West at 1-855-888-7777 and ask for the engineering department.
Hot Springs Minnekahta
- MasTec has started locating utilities along Hot Brook Canyon Road.
- Vantage Point technicians are installing clamshells on customer premises.
- If you have any questions about scheduling or the installation process, please call Golden West at 1-855-888-7777 and ask for the engineering department.
April 4, 2024
Hot Springs Angostura & Minnekahta
- MasTec has crews on site and plans to begin construction as soon as the ground dries up.
- Vantage Point technicians are installing clamshells on customer premises.
- If you have any questions about scheduling or the installation process, please call Golden West at 1-855-888-7777 and ask for the engineering department.
March 22, 2024
Hot Springs Angostura & Minnekahta
- Vantage Point technicians are installing clamshells on customer premises.
- If you have any questions about scheduling or the installation process, please call Golden West at 1-855-888-7777 and ask for the engineering department.
March 15, 2024
Hot Springs Angostura & Minnekahta
- Vantage Point technicians are installing clamshells on customer premises.
- If you have any questions about scheduling or the installation process, please call Golden West at 1-855-888-7777 and ask for the engineering department.
March 8, 2024
Hot Springs Angostura & Minnekahta
- Vantage Point technicians have begun installing clamshells on customer premises.
- If you have any questions about scheduling or the installation process, please call Golden West at 1-855-888-7777 and ask for the engineering department.
February 5, 2024
Golden West will bring fiber optic technology
to rural Hot Springs
Golden West will continue to expand its fiber network in rural Hot Springs, including the Angostura East and Minnekahta West areas. Fiber optic technology allows for greater bandwidth and speeds, offering a more reliable and secure connection to the world for all telecommunications services including internet and phone.
The Fiber to the Home (FTTH) project will convert subscribers from copper cable to long, thin strands of glass called optical fibers, like a strand of hair. These fibers use pulses of light to transmit data and are immune to environmental factors such as electrical currents and water. The multi-year process of upgrading all Golden West customers involves burying about 14,000 miles of fiber-optic cable.
“Fiber optic technology helps brighten the future of the communities and customers we serve,” says General Manager and CEO Denny Law. “Broadband allows telemedicine to reach every corner, plugs rural classrooms and students into the world, and handles the needs of farm fields pulsing with data.”
The Angostura East project covers the area east of Hot Springs, including Maverick Junction and east of Angostura Reservoir. The Minnekahta West project covers a portion of Hwy. 18 west of Hot Springs. Every subscriber who will be upgraded will receive a personal letter in the mail from Golden West soon. Potential new subscribers in these areas should contact Golden West.
Golden West will host an informational open house for subscribers who are part of this year’s construction project. It will be held at 6:30 p.m. Tuesday, Feb. 13, at the Mueller Center Annex at 801 S. 6th St. in Hot Springs. Those in attendance can learn more about the project from Golden West representatives and can talk with contractors who will assist with the local project. Attendees can also enjoy refreshments and register for door prizes.
Three contractors will complete the projects in the rural areas of Hot Springs on behalf of Golden West. MasTec North America will handle construction, and Heberly & Associates will cover easements, permits, and inspections. Vantage Point will serve as the wiring contractor. Golden West will take care of customer service.
FTTH is a multi-stage project that can take up to a year depending on factors such as weather. Current customers will be transitioned to the new fiber optic technology after construction is complete late in 2024 or early in 2025. At that time, customers will be able to subscribe to Golden West’s faster internet speeds.
Currently more than three-quarters of the Golden West service territory is served by fiber. The cooperative is committed to upgrading its entire service territory to fiber within the next three to four years. In addition to rural Hot Springs, Golden West will also complete fiber optic upgrade projects this year in rural Custer, and in areas around Witten and Wood where all necessary rights of way have been secured.
Visit goldenwest.com/FTTH for an overview of the project now and throughout the year. For those who are unable to attend the open house or for things that may come up afterwards, the page also offers the option to submit questions and to fill out a form for a chance to win valuable prizes. Please contact Golden West with any additional questions, concerns, or comments by calling 1-855-888-7777, option 3, and ask for the Engineering Department.