Hot Springs

Two areas in the Hot Springs exchange (rural), including the Angostura East and Minnekahta West areas will be upgraded to Fiber in 2024. 

Contractors:
Wiring Contractor – Vantage Point
Engineering Consultant – Heberly & Associates
Construction Contractor – MasTec North America

Overview Video   Cutover Video

Update Contact Information

Hot Springs Phase 1 2024 FTTP.PNG

2024 PROJECT UPDATE

January 16, 2025
Hot Springs Angostura

  • Fiber splicers are working throughout the project area.
  • When the fibers have been spliced and tested, Golden West technicians will complete the necessary wiring in the new Angostura Golden West office.
  • Customers will be notified by letter before Vantage Point begins scheduling installations.

Hot Springs Minnekahta

  • Fiber splicers are working throughout the project area.
  • When the fibers have been spliced and tested, Golden West technicians will complete the necessary wiring in the Hot Springs Golden West office.
  • Customers will be notified by letter before Vantage Point begins scheduling installations.

January 9, 2025
Hot Springs Angostura

  • Fiber splicers are working throughout the project area.
  • When the fibers have been spliced and tested, Golden West technicians will complete the necessary wiring in the new Angostura Golden West office.
  • Customers will be notified by letter before Vantage Point begins scheduling installations.

Hot Springs Minnekahta

  • Fiber splicers are working throughout the project area.
  • When the fibers have been spliced and tested, Golden West technicians will complete the necessary wiring in the Hot Springs Golden West office.
  • Customers will be notified by letter before Vantage Point begins scheduling installations.

January 2, 2025
Hot Springs Angostura

  • Splicers are connecting the new fibers.
  • When the fibers have been spliced and tested, Golden West technicians will complete the necessary wiring in the new Angostura Golden West office.
  • Customers will be notified by letter before Vantage Point begins scheduling installations.

Hot Springs Minnekahta

  • Splicers are connecting the new fibers.
  • When the fibers have been spliced and tested, Golden West technicians will complete the necessary wiring in the Hot Springs Golden West office.
  • Customers will be notified by letter before Vantage Point begins scheduling installations.

December 19, 2024
Hot Springs Angostura

  • MasTec has completed main line construction.
  • Crews are nearly finished with plowing lines to customer premises.
  • Crews will be off through the end of the year for the Christmas and New Year’s holidays.

Hot Springs FTTH Angostura Construction Area 12-19-24.png

Hot Springs Minnekahta

  • MasTec splicers are working along US Highway 18 and Memorial Road.
  • Crews will be off through the end of the year for the Christmas and New Year’s holidays.

Hot Springs FTTH Minnekahta Construction Area 12-19-24.png