Hot Springs Southeast
The Hot Springs Southeast (rural) will be upgraded to fiber in 2025. This will complete the upgrade of the Hot Springs exchange.
Contractors:
Wiring Contractor – Vantage Point
Engineering Consultant – Heberly & Associates
Construction Contractor – MasTec North America
Overview Video Update Contact Information
Project Updates:
April 10, 2025
- Vantage Point is installing clamshells on customer’s houses.
- MasTec has a crew boring, or drilling and inserting pipe, along Shep’s Canyon Road between SD Highway 71 and Star Dust Pass. This crew is moving west, then will proceed south along SD Highway 71/Cascade Road.
April 3, 2025
- Vantage Point is installing clamshells on customer homes.
- Engineering consultants have been marking the locations to be bored along the construction route.
- Contractors will begin moving materials to their construction yard to prepare for plowing.