Humboldt - Montrose
The Humboldt-Montrose exchange (towns and rural) is scheduled for FTTH upgrades in 2023.
Contractors:
Wiring Contractor - Travis Electric
Engineering Consultant - RVW, Inc.
Construction Contractor - Anderson Underground
2023 PROJECT UPDATE
February 20, 2025
- Travis Electric is trying to reach the remaining customers who have not had their service cut over to fiber.
- If you are a customer who had a line constructed to your home and have not been upgraded to fiber, please call Golden West at 1-855-888-7777 and ask for the engineering department.
February 13, 2025
- Fiber splicers have completed fiber splicing and testing. Heberly & Associates are reviewing the fiber splice test results.
- An area west of Hot Springs has been released to Vantage Point for installations. They are trying to reach customers to schedule appointments.
- As more sections of the project are ready to be cut over to fiber, customers will be notified by letter before Vantage Point begins scheduling installations.
February 6, 2025
- Travis Electric is trying to reach the remaining customers who have not had their service cut over to fiber.
- If you are a customer who had a line constructed to your home and have not been upgraded to fiber, please call Golden West at 1-855-888-7777 and ask for the engineering department.
January 30, 2025
- Travis Electric is nearly finished upgrading customers to fiber.
- If you are a customer who had a line constructed to your home and have not been upgraded to fiber, please call Golden West at 1-855-888-7777 and ask for the engineering department.
January 23, 2025
- Travis Electric is nearly finished upgrading customers to fiber.
- If you are a customer who had a line constructed to your home and have not been upgraded to fiber, please call Golden West at 1-855-888-7777 and ask for the engineering department.